The Tasmanian Government is investing in new and upgraded education infrastructure.
Devonport High School will undergo a $10.5 million redevelopment, providing new state-of-the-art learning facilities for Years 7 to 12 students.

Aerial view of Devonport High School
Current Status
Completion
Construction Commencement
2020
Expected Completion
2022
Funding
State Government - $10.5 million
Community Engagement
The initial stage of community engagement provides opportunity for the school community, local residents and businesses to provide input to help shape the school’s redevelopment.
Phase 1 of community engagement for the redevelopment of Devonport High School was completed in April 2019.
Click here to view the phase 1 consultation outcomes report.
Community engagement is now closed.
Project Initiation & Planning
Project initiation and planning informs development of a concept master plan.
This stage was completed in the first half of 2019.
Development of Master Plan
Development of a concept master plan based on feedback from the community, and input from the project working group and key stakeholders.
This stage was completed in the late 2019.
Community Engagement
The second phase of engagement provides opportunity for the community to review the draft concept master plan via this website and other channels.
Phase 2 of community engagement was completed in March 2020.
Click here to view the phase 2 consultation outcomes report.
Community engagement is now closed.
Design
Design development of the approved concept master plan in readiness for tendering and construction was completed in mid-2020.
Construction
Construction commenced in August 2020.
Completion
Construction is expected to be completed in early 2022.