Current Status
Completion
Construction Commencement
2020
Expected Completion
2021
Funding
State Government - $1.1m
Community Engagement
The initial stage of community engagement informs project initiation and planning.
Community engagement is now closed.
Project Initiation and Planning
Project initiation and planning informs development of a concept master plan.
This stage was completed in 2019.
Development of Master Plan
Development of the concept master plan was completed in late 2019.
Community Engagement
This second stage of engagement provides opportunity for the community to review the concept master plan via this website and other channels.
Community engagement is now closed.
Design
Design development of the approved master plan in readiness for tendering and construction.
This is expected to be completed in the second half of 2020.
Construction
Construction is expected to commence in late 2020.
Completion
Construction works at Dover District School were completed in the first half of 2021.