Kings Meadows High School

The Tasmanian Government is providing choices for students wishing to undertake Years 11 and 12 studies at their local high school.

Kings Meadows High School will undergo an upgrade to provide a new general learning area, staff area, kitchenette, amenities, storage and covered outdoor work area to support Years 11-12 students.

 

Aerial photo of Kings Meadows High School

Current Status

Completion

Construction Commencement

2022

Expected Completion

2022

Funding

State Government - $800,000

Community Engagement

The initial stage of community engagement informs project initiation and planning.

Community engagement is now closed.

Project Initiation and Planning

The project initiation and planning stage informs development of the project master plan and is expected to be completed in the second half of 2020.

Development of Master Plan

This phase will see the development of a master plan – expected to be completed in early 2021.

Community Engagement

The second stage of engagement provides opportunity for the community to review the master plan via this website and other channels.

This is expected to commence in late 2020.

Design

Design development of the approved master plan – expected to be completed in the second half of 2021.

Construction

Construction is expected to commence in the second half of 2021.

Completion

Construction is expected to be completed in the first half of 2022.