The Tasmanian Government is providing options for students wishing to undertake Years 11 and 12 studies at their local high school.
Queechy High School will undergo construction of new general learning areas for Years 11 and 12 students, break out spaces, staff office, amenities and covered walkway.

Aerial photograph of Queechy High School
Current Status
Completion
Construction Commencement
2021
Expected Completion
2022
Funding
State Government - $1.55 million
Community Engagement
The initial stage of community engagement informs project initiation and planning.
Community engagement is now closed.
Project Initiation and Planning
The project initiation and planning stage informs development of the project master plan and was completed in late 2020.
Development of Master Plan
This phase will see the development of a master plan and commenced in January 2021.
Community Engagement
The second stage of engagement provides opportunity for the community to review the master plan via this website and other channels.
This is expected to commence in mid 2021.
Design
Design development of the approved master plan – expected to be completed by mid-2021.
Construction
Construction is expected to commence in the second half of 2021.
Completion
Construction was completed in the first half of 2022.