The Tasmanian Government is investing in new and upgraded education infrastructure.

Taroona High School will undergo a major refurbishment to provide new contemporary learning areas, support spaces, upgraded canteen, and music and drama facilities.

 

Aerial view of Taroona High School

Current Status

Completion

Construction Commencement

2020

Expected Completion

2021

Funding

State Government - $5.5 million

Community Engagement

The initial stage of community engagement informed project initiation and site planning.

Community engagement is now closed.

 

 

Project Initiation and Planning

The project initiation and planning stage informs development of a concept master plan.

Development of Master Plan

Development of the concept master plan has now been completed

Community Engagement

This second stage of engagement provides opportunity for the community to review the concept master plan via this website and other channels.

Community engagement is now closed.

Design

Design development of the approved master plan in readiness for construction was completed in 2019.

Click below to view the design artist renders.

3D Exterior view of construction I

3D Exterior view of construction II

Model animation – Taroona High School

Construction

Construction commenced in January 2020.

Completion

Construction was completed in March 2021.