The Tasmanian Government is providing options for students wishing to undertake Years 11 and 12 studies at their local high school.
Triabunna District School will undergo construction of new learning areas for Years 11 and 12, break out spaces, kitchenette and facilities for school staff, as well as improvements to the kindergarten.

Aerial view of Triabunna District School
Current Status
Completion
Construction Commencement
2021
Expected Completion
2022
Funding
State Government - $800,000
Community Engagement
The initial stage of community engagement informs project initiation and planning.
Community engagement is now closed.
Project Initiation and Planning
The project initiation and planning stage informs development of a concept master plan.
Development of Master Plan
Development of a concept master plan is expected to be completed by end of November 2020.
Community Engagement
This second stage of community engagement provides opportunity for the community to review the master plan via this website and other channels.
Community engagement is now closed.
Design
Design development of the approved master plan in readiness for tendering and construction is expected to be completed by early 2021.
Construction
Construction is expected to commence in the second half of 2021.
Completion
Construction is expected to be completed by early-2022.