Risdon Vale Primary School

Risdon Vale Primary School will undergo an upgrade of classroom layout into a new contemporary classroom configuration incorporating external access to outdoor learning areas.

The project is part of the Tasmanian Government’s $10 million Contemporary Classrooms Program.

Photo of Risdon Vale Primary School

Current Status

Design

Construction Commencement

2023

Expected Completion

2024

Funding

State Government - $950,000

Project Initiation and Planning

The project initiation stage sees the commencement of project planning, documentation and engagement with the school community.

Photo of Risdon Vale Primary School

Community Engagement

The initial stage of community engagement informs development of a site master plan.

Community engagement is now closed.

Get Involved, shaping our future

Development of Master Plan

This phase will see the development of a concept plan for the works.

Photo of Risdon Vale Primary School

Community Engagement

The second stage of engagement provides opportunity for the community to review the concept plan via this website and other channels.

Community engagement is now closed.

Design

Design development of the approved concept plan in readiness for tendering and construction.

This is expected to be completed in 2023.

Photo of Risdon Vale Primary School

Construction

Construction is expected to commence in September 2023.

Photo of Risdon Vale Primary School

Completion

Construction is expected to be completed in the first half of 2024.

Photo of Risdon Vale Primary School