The Saltbush Child and Family Learning Centre will be co-located on the Kingston Primary School site, providing critical services for children and families in the Kingborough Local Government Area.
The new Child and Family Learning Centre (CFLC) will offer a variety of services to support you, all in one place. It is somewhere you and your child can make friends and they can learn as they play. It’s a welcoming place where you can get advice on health and family matters, education and training. For families and young children, its a friendly and caring environment that supports you with health and wellbeing services for children from birth to age 5.

Aerial photo of Kingston Primary School
Current Status
Construction
Construction Commencement
2023
Expected Completion
2024
Funding
State Government - $28 million for six new CFLCs around Tasmania
Community Engagement
The initial stage of community engagement provides an opportunity for parents, carers, families, service providers and the broader community to help shape the new Kingborough Child and Family Learning Centre (CFLC). Phase 1 of the Get Involved campaign for the Kingborough CFLC was conducted from 10 August-18 September 2020.
Click to view the Community Engagement Outcomes and Analytics Report.
Local Enabling Group
A Local Enabling Group (LEG) has been established to contribute and consider ideas throughout project development. The LEG has representation from key local leaders, service providers and community members representing a broad cross section of the Kingborough community.
To register your interest in joining the LEG, please email EYPP@decyp.tas.gov.au.
Want to chat to the project team?
Email us at getinvolved@decyp.tas.gov.au
Project Initiation and Planning
The project initiation and planning stage informs development of a concept master plan and commenced in September 2020.
Development of Master Plan
Development of approved master plan in readiness for tendering and construction – expected to be completed by June 2021
Click to view the Kingborough CFLC master plan .
Community Engagement
This second stage of community engagement provides opportunity for the community to review the draft master plan via this website and other channels.
Community engagement is now closed.
Design
Design development of the approved master plan in readiness for tendering and construction – expected to be completed by early 2022.
Construction
Construction is expected to commence in April 2023.
Completion
Construction of Kingborough Child and Family Learning Centre is expected to be completed in 2024.